Since Microsoft Project's initial release in 1984 it has evolved
into an incredibly powerful and sophisticated project management
tool. One of those sophisticated features is calendars.
As one of my heroes Spiderman says, "with great power comes great
responsibility". As a project manager, you can exploit some of
the cool capabilities with Microsoft Project calendars, but beware,
you could really tie your shorts up in a knot if you start getting
too fancy with project calendars. In addressing this topic, I
want to start off by telling you what Microsoft Project help says
about calendars then give you a few tips to help you avoid Project
Manager hell when trying to develop a meaningful and realistic
project schedule.
There are four types of calendars in Microsoft Office Project 2007: base calendars, project calendars, resource calendars, and task calendars. They are used to determine resource availability, how resources that are assigned to tasks are scheduled, and how tasks are scheduled. Project calendars and task calendars are used to schedule tasks, and if resources are assigned to tasks, resource calendars are used as well. You can modify these calendars to define the working days and hours for the whole project, for groups of resources, for individual resources, and for tasks. These calendars are distinct from the Calendar view, which shows the project schedule in a calendar format.
A base calendar is used as a template that the project calendar, resource calendars, or task calendars are based on. It defines the standard working and nonworking times for the project. It specifies the work hours for each work day, the work days for each week, and any exceptions, such as holidays. You can select a base calendar to use as the project calendar or as the basis for a resource calendar. You can also apply a base calendar to specific tasks.
Project has three default base calendars:
You can use the project calendar to reflect the general working days and hours of your project, as well as regular nonworking times (such as weekends and evenings) and special days off (such as holidays)./p>
The project calendar defines the working and nonworking days and times for tasks. This calendar usually represents your organization's traditional working hours. Project uses this calendar to schedule tasks that do not have resources assigned or that have a task type of fixed duration. By default, the Standard base calendar is used as the project calendar, but you can reflect alternative schedules by using other base calendars.
Resource calendars make sure that work resources (people and equipment) are scheduled only when they're available for work. They affect a specific resource or category of resources. By default, the working time settings in the resource calendar match the project calendar. However, you can customize the resource calendar to show individual schedule information, such as vacations, leaves of absence, or equipment maintenance time. By clicking Change Working Time on the General tab of the Resource Information dialog box, you can edit resource calendars to indicate nonworking time. You can also create or assign different base calendars for individual resources, or groups of resources, to indicate specific working hours. For example, you can assign a resource to a calendar that you created for carpenters who may be working during a time that is different from other workers.
Task calendars make it possible to schedule tasks during nonworking time, as defined by the project calendar or resource calendar. For example, you can set up a task calendar if you have a task that needs to be worked on overnight or through the weekend. You create a task calendar in the Change Working Time dialog box as a new base calendar. You then apply the base calendar to a task by using the Advanced tab in the Task Information dialog box. If you have applied a task calendar to a task that already has assigned resources, by default, the task is scheduled for the working times that the task calendar and resource calendars have in common. If you want to schedule the task by using only the task calendar, select the Scheduling ignores resource calendars check box on the Advanced tab in the Task Information dialog box.
Microsoft Project calendars can give you tremendous flexibility in how you define your project. Just make sure you balance precision with simplicity and avoid making managing your Microsoft Project plan a project in and of itself.